2026-10-09
On a three-shift line, wear parts are consumed by tons, not by weeks. A replacement plan written on the calendar keeps drifting away from what the machine is actually doing. The points below put the schedule on measured use instead.
Plan by Tonnage, Not by Calendar
On the same line, daily output in the busy season and in the slow season can differ by 20% to 30%. A calendar plan will always be off. It counts days; the part is consumed by tonnage.
Write the plan in tons. A part is due when the tonnage it has processed reaches its limit, not when a date on the wall arrives. When the calendar and the tonnage disagree, the tonnage is what decides.
Keep a Four-Point Record
A tonnage plan only works if the tonnage is written down. For every wear part, keep four fields.
- Installation date
- Installation tonnage
- Replacement tonnage
- Replacement reason: worn through, broken, or drop in efficiency
The reason field is the one most often left empty, and it is the one that tells you what to fix. Worn through, broken and falling efficiency are three different problems with three different causes. The installation date ties the record to the maintenance log; the two tonnage fields are what turn the part into a life figure.
Four fields per part is not much work. After a few replacements, the record shows which position wears fastest and how it fails. Two lines running the same part under the same conditions will still produce different life figures; the record is there to give your line its own number.
Key Life-Limited Parts
These are the parts that usually drive the schedule:
- Jaw plates
- Blow bars
- Hammers
- Cone liners
- Screen media
- Conveyor belts
- Grinding balls
Anything on this list should have a four-point record and a stock decision behind it. The list is not a wish list for stock; it defines which parts get measured.
Spare Parts Strategy
Stock depth follows how the part is used.
- Common wear parts: one set in use, one set in stock.
- Universal parts (bearings, V-belts, seals): one spare per machine model.
Common wear parts are the ones the tonnage plan will call for; universal parts are kept for the machine, not for the schedule. The aim is to have the right part on the shelf when the tonnage says it is due, not to carry everything.
When to Change: Thickness and Output
Waiting until a part is worn through is the most expensive way to change it.
That change is not free of side effects either: it often damages the parts in the next process stage as well, so one worn-out item becomes two.
Set the change point on two indicators: thickness measurement and production tonnage. Thickness tells you the condition of the part; tonnage tells you how much work it has done. Use both.
Bring the Supplier In
Give the supplier the machine model and the working conditions. Ask for a life range by tonnage rather than by time.
The supplier sees many machines doing the same job; your job is to give them the model and the conditions so the answer matches your line. A range built on the application beats a number guessed from how long the part lasted last time.